How to Prepare the SWC Trimester Report, Step by Step
Dates, budget headings, utilization, variance remarks and the technical report for NGOs and INGOs in Nepal, with a free Excel format to follow along.
If your organization runs a project under an agreement with the Social Welfare Council (SWC), you report on it three times a year. The first trimester report is due in the first week of Mangsir, so the work starts now, while the Kartik bills and vouchers are still fresh.
This guide walks through the report the way we prepare it for our own NGO and INGO clients. It follows the layout of our free SWC trimester report format, so you can open the Excel file and fill it as you read.
The three reporting periods
The Nepali fiscal year is split into three trimesters. Each report goes to SWC in the first week of the month after the trimester ends.
| Trimester | Period covered | Submit to SWC |
|---|---|---|
| First | Shrawan 1 to Kartik end | First week of Mangsir |
| Second | Mangsir 1 to Falgun end | First week of Chaitra |
| Third | Chaitra 1 to Ashad end | First week of Shrawan |
These dates also appear in our compliance calendar, where you can add them to your own phone or computer calendar.
Always read the reporting clause in your own SWC agreement as well. If SWC or your donor has asked for a different format or date for your project, that instruction comes first.
What the report contains
A trimester report has two halves.
- Financial progress: what you spent against the approved budget, heading by heading.
- Technical progress: what you achieved against the activity targets in the agreement.
SWC reads the two together. A heading that is 80 percent spent while its activity is 10 percent complete will raise a question, and so will the reverse.
Step 1: Collect the project details
Before any numbers, gather the details that go at the top of every sheet. Copy them exactly as they appear in the SWC agreement.
- Organization name and project name
- SWC agreement or project number
- Donor name
- Project start and end dates in BS
- Total approved budget and the approved budget for the current fiscal year
- Amount received from the donor to date
- Project bank account details
- Names and designations of the person preparing the report and the person approving it
The total project budget and the budget for this fiscal year are two different figures. Mixing them up is one of the most common errors we see, and it spoils every percentage that follows.
Step 2: Use the budget headings from your agreement
List the approved budget by heading, in the same words used in the SWC agreement. Split them into two groups:
- Administrative expenses, such as staff salary, office rent, communication, stationery, transport and audit fee.
- Programme expenses, meaning the costs of the project activities themselves, such as trainings, surveys, awareness programmes, materials and monitoring.
Do not rename headings to make them read better. The person checking your report will compare it with the agreement line by line.
Our Excel format comes with sample headings already typed in so you can see how it works. Replace every one of them with the headings from your own agreement before you start.
Step 3: Enter expenses in two columns
For each heading you need two figures:
- Expense up to the previous trimester. Take this from the closing figure of your last submitted report. For a first trimester report this is zero.
- Expense in this trimester. Take this from your ledger for the period only.
The total expense to date, the balance budget and the utilization percentage then follow by simple arithmetic. Utilization is the total expense to date divided by the approved budget for the year.
Two quick checks before you move on:
- The "up to previous trimester" figures should match your last report exactly. If they differ, find out why before you submit anything.
- The total of this trimester's expenses should agree with the project ledger and the bank statement for the same dates.
Step 4: Compare utilization with where you should be
Spending is rarely perfectly even, but a simple yardstick helps. If the budget were spent evenly through the year, you would have used about one third of it by the end of the first trimester, two thirds by the end of the second, and all of it by the end of the third.
Our format uses this as the expected level and highlights any heading that is more than 10 percentage points away from it, until you explain the difference in the remarks column. The 10 point mark is our own working rule for deciding what needs an explanation. It is not an SWC limit.
Not every gap is a problem. A training programme planned for the second half of the year will naturally show low spending in the first trimester. What matters is that the reader can see why.
Step 5: Write remarks that answer the question
A good remark is short and specific. Compare these two:
- Weak: "Activity delayed."
- Better: "Skill training batch 2 moved to Poush because the venue was unavailable in Kartik. Full budget will be used by the third trimester."
State the reason, and say when the money will be used or whether the budget will be revised. If a heading is overspent, say where the extra funds came from and whether the donor or SWC has approved the change.
Step 6: Fill the technical progress
For each activity in the agreement, enter:
- the unit of measurement (persons trained, meetings held, kits distributed)
- the annual target
- progress up to the previous trimester
- progress in this trimester
The progress percentage follows from these. Then write three short sections in plain language:
- Key achievements in this trimester. Numbers first, then one or two sentences on what changed for the target group.
- Challenges and what you did about them. Be honest. Reviewers trust a report that names problems and shows a response.
- Plan for the next trimester. The activities and approximate months, matched to the remaining budget.
Keep the technical report consistent with the financial one. If the technical sheet says an activity is complete, the financial sheet should show the money spent on it.
Step 7: Report the taxes paid
Record the TDS, VAT and other taxes, such as social security tax, paid to the government during the trimester. Keep the deposit slips and returns in your file. These are also the first things an auditor asks to see at year end, so a clean record now saves time later.
Step 8: Run the final checks
Before signing, check these five points:
- The sum of your budget headings equals the approved budget for the fiscal year.
- Every heading with a large gap from the expected level has a remark.
- Expenses to date agree with the books and the bank statement.
- Financial and technical figures tell the same story.
- The report is signed and dated by the right people, and a copy is saved with the supporting vouchers.
Mistakes we see most often
- Budget headings that do not match the agreement word for word
- Opening figures that differ from the last submitted report
- Large variances with no explanation
- The total project budget used in place of the annual budget
- Taxes paid left out
- Technical progress written last, in a rush, and not matching the finances
Download the format
You can use the same layout we use for our clients. It includes a blank format and a filled example from a fictional project so you can see how each sheet reads.
The format is a working aid prepared by P.S.G. & Associates. It is not an official SWC form. If SWC or your donor requires a specific template for your project, use that one and carry the same figures across.
Frequently asked questions
Who has to submit SWC trimester reports?
NGOs and INGOs implementing projects under an SWC agreement report on each trimester of the project. Check your own agreement for the exact requirement.
When is the first trimester report due?
In the first week of Mangsir. It covers Shrawan 1 to Kartik end.
Does the first trimester report need figures from a previous report?
No. The "up to previous trimester" column is zero in the first trimester, because there is nothing earlier in the fiscal year to carry forward.
What do I do if spending is far below plan?
Say why in the remarks and state when the spending will happen. If the delay will change the plan or the budget, talk to your donor and SWC early instead of waiting for the year end.
Does the annual audit use the trimester reports?
Auditors read them alongside the books. Differences between the trimester figures and the ledger are easy to spot, which is another reason to reconcile before you submit.
Can P.S.G. & Associates prepare our SWC reports?
Yes. We prepare trimester and annual reports for NGOs and INGOs, audit their projects and help with SWC monitoring and evaluation. Contact us and mention SWC reporting.
P.S.G. & Associates, Chartered Accountants, is registered with the Institute of Chartered Accountants of Nepal (Firm No. 1220). This article is general guidance and does not replace your SWC agreement or advice on your specific project.